Bridge Deck Span Installation Postponed

Due to high winds in the forecast Saturday afternoon the installation of the bridge deck span has been postponed until Sunday at 7 a.m. The work that was scheduled for Saturday and Sunday will now take place on Sunday and Monday and the existing bridge will remain open today.

The existing Johnson Street Bridge will now be closed from 7 a.m. Sunday until 5 p.m. on Monday to all pedestrians, cyclists, and drivers as the crane barge will be parked directly underneath the existing bridge during the installation. During the closure, traffic delays are expected and pedestrians, cyclists and drivers should plan to use the Bay Street Bridge.

Note: The dates and times above remain subject to change and are weather dependent as the steel pieces cannot be lifted during high winds.

For more information visit: www.johnsonstreetbridge.com